Sr. | Doc. Name | Issue date | Project System |
01 | LAF Re-Qualification Protocol & Annex | Jan., 2021 | LAB Area |
02 | Weighing booth Re-Qualification Protocol & Annex | Jan., 2021 | Dispensing Area |
03 | AHU (TANTA)Test Report (INSTALLED HEPA FILTER LEAK TEST) | Jan., 2021 | Solid Area |
04 | AHU -13 Test Report (INSTALLED HEPA FILTER LEAK TEST) | Jan., 2021 | Solid Area |
05 | AHU (TANTA)Test Report (INSTALLED HEPA FILTER LEAK TEST) | Jan., 2021 | Solid Area |
06 | AHU -02 Test Report (INSTALLED HEPA FILTER LEAK TEST) | Jan., 2021 | Warehouse Area |