Sr. | Doc. Name | Doc No. | Issue date | Project System |
01 | AIR SHOWER Operation Qualification Protocol | OQP-L-02324 | 8/2/2024 | production |
02 | AIR VELOCITY VERIFICATION TEST REPORT | FVT-00624 | 8/2/2024 | micro |
03 | AIR VISUALIZATION TEST REPORT | AVU-00924 | 8/2/2024 | micro |
04 | AIR VISUALIZATION TEST REPORT | AVU-00824 | 8/2/2024 | micro |
05 | INSTALLED HEPA FILTER LEAK TEST REPORT | HLT-02024 | 8/2/2024 | production |
06 | PASS BOX Operation Qualification Protocol | OQP-L-02424 | 8/2/2024 | production |
07 | AIR VELOCITY VERIFICATION TEST REPORT | FVT-00224 | 8/2/2024 | Lab Area |
08 | AIR VISUALIZATION TEST REPORT | AVU-00224 | 8/2/2024 | Lab Area |
09 | FILTER AIR VELOCITY VERIFICATION TEST REPORT | FVT-00324 | 8/2/2024 | production |
10 | AIR VISUALIZATION TEST REPORT | AVU-00324 | 8/2/2024 | production |