Sr. Doc. Name Doc No. Issue date Project System 1 Testing, Adjusting & Balancing TAB-04020 April,2020 Sampling, production, Warehouse and packaging area 2 IQ protocol and Annex IQP-H-03020 April,2020 Production area 3 OQ protocol and Annex OQP-H-04120 April,2020 Production area…
Jedco- IQ, OQ & TOP
Sr. Doc. Name Doc No. Issue date Project System 01 IQ Protocol for Hard Gelatin IQP-H-02620 Apr.,2020 IQ 02 IQ Annex for Hard Gelatin IQP-H-02620 Apr.,2020 IQ 03 IQ Protocol for Sampling Area IQP-H-02720 Apr.,2020 IQ 04 IQ Annex for Sampling Area IQP-H-02720 Apr.,2020 IQ 05 IQ Protocol for Weighing Area IQP-H-02820 Apr.,2020 IQ 06 IQ Annex for Weighing Area IQP-H-02820 Apr.,2020 IQ 07 IQ Protocol for Micro Area IQP-H-02920 Apr.,2020 IQ 08 IQ Annex for Micro Area IQP-H-02920 Apr.,2020…
Hi Pharma-LAF Qualification
Sr. Doc. Name Doc No. Issue date Project System 1 LAF Qualification Protocol and Annex 01.01 WH-DL-02 02/03/2020 Hormonal Dispensing LAF 2 LAF Qualification Protocol and Annex 01.01 WH-DL-01 02/03/2020 Non Hormonal Dispensing LAF 3 LAF Qualification Protocol and Annex 01.01 WH-SL-02 02/03/2020 Hormone Sampling LAF 4 LAF Qualification Protocol and Annex 01.01 WH-SL-01 02/03/2020 Non Hormone Sampling LAF 5 LAF Qualification Protocol and Annex 01.01 QC-LF-01 02/03/2020 Micro LAF …
Global Energy(Cairo West Power Plant)-TAB
Sr. Doc. Name Doc No. Issue date Project System 1 Testing, Adjusting & Balancing Report TAB-03920 01/03/2020 Control Electrical Building (Ground Floor) …
Misr Cosmatic-LAF 2
Sr. Doc. Name Doc. No. Issue date Project System 01 LAF Operation qualification Protocol OQP-L-01320 04/12/2019 MISR COSMATICS (LAF 2) 02 LAF Operation qualification Protocol ANNEX1 OQP-L-01320 04/12/2019 MISR COSMATICS (LAF 2)…
Misr Cosmatic-LAF 4
Sr. Doc. Name Doc. No. Issue date Project System 01 LAF Operation qualification Protocol OQP-L-01420 04/12/2019 MISR COSMATICS (LAF 4) 02 LAF Operation qualification Protocol ANNEX1 OQP-L-01420 04/12/2019 MISR COSMATICS (LAF 4)…
MEVAC-Qualification
Sr. Doc. Name Doc No. Issue date Project System 01 IQ Protocol for Ground Floor IQP-H-02420 Mar.,2020 IQ 02 IQ Annex for Ground Floor IQP-H-02420 Mar.,2020 IQ 03 IQ Protocol for First Floor IQP-H-02520 Mar.,2020 IQ 04 IQ Annex for First Floor IQP-H-02520 Mar.,2020 IQ 05 OQ Protocol for Ground Floor OQP-H-03420 Mar.,2020 OQ 06 OQ Annex for Ground Floor OQP-H-03420 Mar.,2020 OQ 07 OQ Protocol for First Floor OQP-H-03520 Mar.,2020 OQ 08 OQ Annex for First Floor OQP-H-03520 Mar.,2020…
Vaccine Valley-Qualification, TAB & TOP
Sr. Doc. Name Doc No. Issue date Project System 01 HVAC Installation Qualification (Production Building) IQP-H-05519 Dec.,2019 IQ 02 HVAC Operation Qualification (Production Building) OQP-H-10919 Dec.,2019 OQ 03 TESTING, ADJUSTING & BALANCING (Production Building) TAB- 11219 Dec.,2019 TAB 04 HVAC Installation Qualification (QC Building) IQP-H-05619 Dec.,2019 IQ 05 HVAC Operation Qualification (QC Building) OQP-H-11019 Dec.,2019 OQ 06 TESTING, ADJUSTING & BALANCING (QC Building) TAB- 11019 Dec.,2019 TAB 07 Turn Over Package (Production Building) TOP-01520 Dec.,2019 TOP 08 Turn Over…
Semco (Warehouse)-TAB
Sr. Doc. Name Doc. No. Issue date Project System 01 TESTING, ADJUSTING & BALANCING REPORT TAB-03820 15/11/2019 Warehouse (Block F)…
Misr Cosmatic-Qualification
Sr. Doc. Name Doc. No. Issue date Project System 01 Operation qualification Protocol OQP-L-01520 04/12/2019 Misr Cosmatic (Tunnel) 02 Operation qualification Annex OQP-L-01520/01 04/12/2019 Misr Cosmatic (Tunnel)…