Sr. Doc. Name Doc. No Issue date Project system 1 BIO SAFETY CABINET  RE-QUALIFICATION PROTOCOL RQP-L-30725 Nov, 2025 Micro Lab AREA…

LAMAR

Sr. Doc. Name Doc. No Issue date Project system 1 BIO SAFETY CABINET  RE-QUALIFICATION PROTOCOL RQP-L-30725 Nov, 2025 Micro Lab AREA…

APEX Pharma-Refrigerator-THM-KSA

No. Doc. Name Issue date Doc. No. Area 01 Re-Qualification Protocol (QCE-037) Nov., 2025 PQP-M-01225 Raw material retained sample (QC-033) 02 Re-Qualification Annex (QCE-037) Nov., 2025 PQR-M-01225 Raw material retained sample (QC-033) 03 Re-Qualification Turn Over Package (QCE-037) Nov., 2025 TOP-PQ-01225 Raw material retained sample (QC-033)…

INAD PHARMA

Sr. Doc. Name Doc No. Issue date Project System 01 INSTALLED ABSOLUTE HEPA FILTER LEAK TEST REPORT(AHU-01) HLT-16725 Nov., 2025 Strile 02 INSTALLED ABSOLUTE HEPA FILTER LEAK TEST REPORT(AHU-03) HLT-16825 Nov., 2025 Strile 03 INSTALLED ABSOLUTE HEPA FILTER LEAK TEST REPORT(AHU-05) HLT-17025 Nov., 2025 Strile 04 INSTALLED ABSOLUTE HEPA FILTER LEAK TEST REPORT(AHU-08) HLT-17125 Nov., 2025 Strile 05 INSTALLED ABSOLUTE HEPA FILTER LEAK TEST REPORT(AHU-10) HLT-17225 Nov., 2025 Strile 06 INSTALLED ABSOLUTE HEPA FILTER LEAK TEST REPORT(AHU-11) HLT-17725 Nov., 2025…

APEX Pharma-Refrigerator-THM-KSA

No. Doc. Name Issue date Doc. No. Area 01 Re-Qualification Protocol (QCE-016) Nov., 2025 PQP-M-01125 Methodology Lab. (QC-019) 02 Re-Qualification Annex (QCE-016) Nov., 2025 PQR-M-01125 Methodology Lab. (QC-019) 03 Re-Qualification Turn Over Package (QCE-016) Nov., 2025 TOP-PQ-01125 Methodology Lab. (QC-019)…

BARKOUKY

Sr. Doc. Name Doc. No Issue date Project system 1 WATER FLOW RATE MEASUREMENTS TEST REPORT WBR-01925 Nov, 2025 Office AREA 2 FCUs AIR FLOW RATE MEASUREMENT TEST REPORT AFR-02025 Nov, 2025 Office AREA…

APEX Pharma-Refrigerator-THM-KSA

No. Doc. Name Issue date Doc. No. Area 01 Re-Qualification Protocol (QCE-011) Nov., 2025 PQP-M-01025 Instrumental Lab. (QC-017) 02 Re-Qualification Annex (QCE-011) Nov., 2025 PQR-M-01025 Instrumental Lab. (QC-017) 03 Re-Qualification Turn Over Package (QCE-011) Nov., 2025 TOP-PQ-01025 Instrumental Lab. (QC-017)…

GYPTO PHARMA

Sr. Doc. Name Doc. No Issue date Project system 1 LAF RE-QUALIFICATION PROTOCOL ( FILLING &COPING AREA) RQP-L-29725 Oct, 2025 FILLING &COPING AREA 2 LAF RE-QUALIFICATION PROTOCOL( STERILE AREA) RQP-L-29625 Oct, 2025 STERILE AREA 3 PASS BOXES RE-QUALIFICATION PROTOCOL RQP-L-29525 Oct, 2025 STERILE AREA…

KINETIC ENGINEERING &CONTRACTING MEP

Sr. Doc. Name Doc. No Issue date Project system 1    FCU AIR FLOW RATE MEASUREMENTS TEST REPORT AFR-01925 Nov, 2025 EFFERVESCENT & POWDER AREA 2 WATER FLOW RATE MEASUREMENTS TEST REPORT WBR-01825 Nov, 2025 EFFERVESCENT & POWDER AREA…